The White Falcon

Tölublað

The White Falcon - 12.06.1987, Blaðsíða 5

The White Falcon - 12.06.1987, Blaðsíða 5
New fuel depot to meet growing needs of base by Lt. Cmdr. Thomas Hilferty ROICC Office, Keflavik fl new fuel depot and receiving facility is being built at Helguvik, four miles from the base. Designed to improve the readiness and operational capability of the NATO Base, its construction is in seven phases and is expected to take 12 years, at a cost of $160 million. The Defense Force uses three types of fuel: diesel, aviation and gasoline. Diesel and aviation fuel are offloaded and stored in Hvalfjordur (Whale Bay), about 70 miles away. This fuel is taken by coastal tanker to the Keflavik-Njardvik municipal pier, and pumped to the base. Gasoline Is offloaded and stored in Hafnarfjordur, then delivered to the base by truck. The new Helguvik facility will greatly improve the offloading, storing and transportation of all three fuel products used by the NATO Base. Phase I began in January 1984 and was recently completed. Two reinforced-concrete, steel-lined fuel tanks, a pipeline from Helguvik to the base and a pump station were built. Phase II, now underway, involves building a rock jetty, a refueling platform, various supporting facilities for operations and fire protection, and fuel pipelines from the platform to the depot. Jetty construction began in June 1986. When finished it will be able to handle ships up to 35,000 tons. The jetty is designed to absorb the energy of incoming waves. A thick layer of armor stone protects the core material underneath. The design was chosen to minimize costs by using rocks available at Helguvik. Each armor stone weighs between two and eight tons. Because the design is unique, small scale model studies were conducted in Canada, simulating the topography and worst storm conditions anticipated in the next 100 years. The part of the jetty above water is truly the 'tip of the iceberg." Most of the rocks are under water. The core is being placed by a split-bottom barge, and the armor stone is placed by a crane. To be sure it is placed accurately, a sophisticated marine surveying system makes sectional profiles every 50 feet. The core closest to shore is developed first. As the core Is finished, the armor stone is placed to protect it from erosion. Weather conditions halted placement above 55 feet below sea Aerial view of Helguvik fuel facility (U.S. Navy photo). level between December and April. Core material was placed below 55 feet, where the potential for erosion is minimal. As of April 30, approximately half of the core material and 35 percent of the armor stone had been placed. The refueling platform is supported by huge concrete caissons that rest on a level bed of gravel 55 feet below sea level. These hollow structures are made at Straumsvik at the aluminum plant, about 30 miles from Helguvik. The base and lower walls of each caisson are completed on the plant's launching platform, lowered into the water during high tide and floated to the next staging area. The walls are constructed in 12-foot lifts at separate staging areas. Each area is about ten feet deeper than the previous one. Building a lift, then floating it during high tide to the next deeper staging area will be repeated for all five caissons. They will be taken by sea for final placement at Helguvik in August. When Phase II is finished in December 1988, the Defense Force will be able to offload and store fuel at Helguvik and pump it directly to the NATO Base. Phase III began in May 1987 and is scheduled to finish in March 1989. It involves building three more fuel tanks, three truck-fill areas, depot piping and site utilities. Phases IV through VII involve building six more fuel tanks and depot piping in Helguvik, various smaller fuel tanks and piping on the base, demolition of the tanks at the old Keflavik depot and removing the old fuel lines from the base to the Keflavik commercial pier. Upon completion of all seven phases in the mid- 1990's, the NATO Base will have enhanced its capacity to offload and store fuel products at Helguvik and quickly distribute this fuel to critical locations throughout the NATO Base. June 12, 1987 5

x

The White Falcon

Beinir tenglar

Ef þú vilt tengja á þennan titil, vinsamlegast notaðu þessa tengla:

Tengja á þennan titil: The White Falcon
https://timarit.is/publication/382

Tengja á þetta tölublað:

Tengja á þessa síðu:

Tengja á þessa grein:

Vinsamlegast ekki tengja beint á myndir eða PDF skjöl á Tímarit.is þar sem slíkar slóðir geta breyst án fyrirvara. Notið slóðirnar hér fyrir ofan til að tengja á vefinn.