Upp í vindinn - 01.05.2009, Blaðsíða 38

Upp í vindinn - 01.05.2009, Blaðsíða 38
Evaluating the fire safety performance Case Population Total 1 4200 2 3700 2* 3700 3 2500 3* 2500 Evacuationtime t (min.) evac ' ' 2ndfloor P'floor 3:30°** 7:50° 3:30°** 7:10° 3:30°** 9:20° 3:30°** 5:20° 3:30°** 7:00° 3 vents 2nd floor P'floor 1.57 1.60 1.57 1.74 1.57 1.34 1.57 2.34 1.57 1.79 No vents 2ndf1oor P’floor 1.33 1.09 1.33 1.19 1.33 0.91 1.33 1.59 1.33 1.21 Criticaltimest „ crit 3 vents 5:30° 12:30° Novents 4:40° 8:30° (*) 1 exitblocked (**) estimated time Table 2: Population, evacuation times and safety factors for various configuration cases. the evacuation routes. Therefore, engineers should take a safety factor higher than 1. How high depends mainly on how conservative were the choices made by the engineer for the simulation. The evacuation is simulated for different number of occupants (see Table 2) in zone 1 (see Figure 4), but with fixed number of occupants in Zones 2 and 3 (100 and 600).The corresponding evacuation times are compared to the critical times defined earlier, and K , is calculated. As recommended by guidelines, tests with one of the exit doors blocked are also simulated (case 2* and 3*). The results show that the safety is not sufficient in the worst case (Ksafc = 0.91 < 1) for 3700 people if vents are not functioning and one exit door closed (case 2*). For 2600 people, the safety level is sufficient (K ifc > 1.2), even with the 2 failures in the safety system. Prescriptive based methods based on recommendations from building regulations [9] allow calculating the maximum number of people as a function of the size and number of emergency exits. Applying this method to the skating hall gives a maximum close to 1800 people. Conclusion In this article, we have described the fire safety investigation process for new or existing Figure 4: Evacuation modeling in case 2: population at t= 0 on 1 st (left) and 2nd floor (right). Figure 5 : Evacuation modeling in case 2: population at t= 3 min. on 1 st (left) and 2nd floor (right). building, using both CFD and evacuation models. As an example, the fire safety of the skating hall in Reykjavik is tested in a very different configuration than the intended use was, with a rock concert hosting about 3 times the normal population of the hall. The fire and smoke simulation carried out using the CFD software FDS gave the critical time for evacuation, which was then compared to results from an evacuation model built with BuildingExodus, tested for various populations and exit conditions. It appeared that the evacuation time remained smaller than a critical time based on visibility conditions, showing that both thc smoke exhaustion system in the roof and the emergency routes created a sufficient level of safety in the case safety devices work properly. However, failures must be considered while assessing the safety of a building, and authorities and fire safety engineers should always make conservative choices and carry out sensitivity analysis to account for possible unexpected problems. The performance based evacuation simulation suggested that the level of safety wasn’t sufficient for 3600 people (case 2) in the likely case of 2 failures in the system. The prescriptive method suggested a significantly lower value close to 1800 people, but the safety level for 2600 people (K fc <1.2; lVz minute safety delay) was confirmed to be sufficient considering the conservative choices made during the simulations. REFERENCES [1] Karlsson B., Quintiere J.G. (2000):"Enclosure Fire Dynamics", CRC Press. [2] Drysdale D.D. (1992): "An Introduction to Fire Dynamics", Wiley-lnterscience. [3] SFPE Handbook of Fire Protection Engineering, 2nd ed. (1995): National Fire Protection Association. [4] Fire Dynamic Simulator FDS and Smokeview homepage: http://www.fire.nist. gov/fds/ [5] BuildingExodus homepage, http://fseg.gre. ac.uk/exodus/ [6] Bryan J.L. (1995):"Behavioral response to fire and smoke", SFPE Handbook of Fire Protection Engineering", 2nd ed., National Fire Protection Association. [7] PaulsJ.(1995):"Movementof people",SFPE > Handbook of Fire Protection Engineering", 2nd ed„ National Fire Protection Association. [8] Nelson H.E, MacLennan H.A. (1995): "Emergency movement", SFPE Handbook of Fire Protection Engineering" 2nd ed., National Fire Protection Association. [9] Byggingarreglugerð 441/1998. 38 I ... upp í vindinn
Blaðsíða 1
Blaðsíða 2
Blaðsíða 3
Blaðsíða 4
Blaðsíða 5
Blaðsíða 6
Blaðsíða 7
Blaðsíða 8
Blaðsíða 9
Blaðsíða 10
Blaðsíða 11
Blaðsíða 12
Blaðsíða 13
Blaðsíða 14
Blaðsíða 15
Blaðsíða 16
Blaðsíða 17
Blaðsíða 18
Blaðsíða 19
Blaðsíða 20
Blaðsíða 21
Blaðsíða 22
Blaðsíða 23
Blaðsíða 24
Blaðsíða 25
Blaðsíða 26
Blaðsíða 27
Blaðsíða 28
Blaðsíða 29
Blaðsíða 30
Blaðsíða 31
Blaðsíða 32
Blaðsíða 33
Blaðsíða 34
Blaðsíða 35
Blaðsíða 36
Blaðsíða 37
Blaðsíða 38
Blaðsíða 39
Blaðsíða 40
Blaðsíða 41
Blaðsíða 42
Blaðsíða 43
Blaðsíða 44
Blaðsíða 45
Blaðsíða 46
Blaðsíða 47
Blaðsíða 48
Blaðsíða 49
Blaðsíða 50
Blaðsíða 51
Blaðsíða 52
Blaðsíða 53
Blaðsíða 54
Blaðsíða 55
Blaðsíða 56
Blaðsíða 57
Blaðsíða 58
Blaðsíða 59
Blaðsíða 60
Blaðsíða 61
Blaðsíða 62
Blaðsíða 63
Blaðsíða 64
Blaðsíða 65
Blaðsíða 66
Blaðsíða 67
Blaðsíða 68
Blaðsíða 69
Blaðsíða 70
Blaðsíða 71
Blaðsíða 72
Blaðsíða 73
Blaðsíða 74
Blaðsíða 75
Blaðsíða 76
Blaðsíða 77
Blaðsíða 78
Blaðsíða 79
Blaðsíða 80
Blaðsíða 81
Blaðsíða 82
Blaðsíða 83
Blaðsíða 84

x

Upp í vindinn

Beinir tenglar

Ef þú vilt tengja á þennan titil, vinsamlegast notaðu þessa tengla:

Tengja á þennan titil: Upp í vindinn
https://timarit.is/publication/1929

Tengja á þetta tölublað:

Tengja á þessa síðu:

Tengja á þessa grein:

Vinsamlegast ekki tengja beint á myndir eða PDF skjöl á Tímarit.is þar sem slíkar slóðir geta breyst án fyrirvara. Notið slóðirnar hér fyrir ofan til að tengja á vefinn.