Tímarit Verkfræðingafélags Íslands


Tímarit Verkfræðingafélags Íslands - 01.02.1984, Blaðsíða 16

Tímarit Verkfræðingafélags Íslands - 01.02.1984, Blaðsíða 16
jects that are planned in the near future are also listed. A number of small scale hydropower stations are operated privately in the country (mainly by farmers) but these are not listed in the table. Similarly a large number of small scale hydropower stations from the ear- ly days of electrification of the country are now out of use and therefore not listed in the table. Some 99% of the population have access to electricity from public utilities, but 1% from private utilities. Nearly all hydropower stations in the country up to 8 MW capacity have been designed by lcelandic engineers. During the period 1935—1960 a series of three power plants were built in the river Sog (No. 2, 15 and 20 in Table 1). The prin- cipal consultant on this project was a Norwegian engineering firm. The first large hydropower plant in lceland was Búrfell in the Thjórsá river (240 MW) which was commissioned in 1969. The World Bank partly financed the project and in accordance with their rules demanded that the design work be under the responsibility of an engineer- ing firm with experience in building such large hydroprojects. The owner of the project, the National Power Com- pany, engaged an engineering company from the U.S.A. for the work. Since then two large hydropower plants have been built in the Tungnaá river, a tributary to the Thjórsá river, Sigalda 150 MW and Hrauneyjafoss 210 MW. The former was partly financed by the World Bank. In both cases the National Power Company assigned the design work to consortiums of foreign and Icelandic engineering firms on a joint venture basis. In the case of Sigalda (commissioned in 1977), the companies were from Switzerland and lceland, but in Hrauneyjafoss (commissioned in 1981) the companies were from the U.S.A. and Iceland. In the case of the Hrauneyjafoss project the National Power Company requested that most of the construction drawings should be made by the Icelandic firm whereas inspection of the drawings and the calculations made by the suppliers of the electrical and mechanical equipment was done jointly by the two firms. The National Power Company has entrusted the planning and design of the hydropower projects now under construction to Icelandic engineers. As can be seen in Table 1 there are plans to double the installed hydropower capacity in the country. This will probably be done within the next two decades, the exact timing of the individual projects being dependent 8 - TÍMARIT VFÍ 1984 on future decisions on whether to in- crease energy intensive industries. Since 1958, 12 main master plans have been made for the development of power projects in individual rivers or river systems. Of these only 2 have been made by foreign consultants (from the U.S.A. in 1960 and from Norway in 1966). The foreign consultants based their work largely on data and plans supplied by Icelandic engineers and hydrologists. The methodologies of the two master plans made by the foreign consultants have, however, been adopted in later plans. Due to the harsh climate in the coun- try the design of power lines is a highly skilful task. In the uninhabited highland interior of the country the ice load on the wires can for example be up to 54 kg/m and the wind speed caii reach up to 65 m/s; these maximum values do however never occur at the same time. The accumulated length of high voltage power lines in Iceland was in 1982 just over 10,000 km, thereof the main power lines with a voltage ranging from 33 to 220 kV are nearly 3,100 km in length. Until about 1950, most power lines were designed by foreign consultants, but since then engineers of the State Electric Power Works have done the design work for all but the main power lines. Until the mid 1970’s the main high voltage power lines were designed by foreign consultants, but recently the design work has been taken over by local engineers. A similar development has taken place in the construction in- dustry. All major hydropower plants and transmission lines built until the mid 1970’s were constructed by foreign contractors or a consortium of foreign and local contractors. The civil works for the Hrauneyjafoss hydropower plant were, however, mainly assigned to Icelandic contractors. Based on this ex- perience it may be assumed, that future constructions of this kind will be carried out by local contractors. In 1982 an Icelandic consulting engineering firm was for the first time involved in the investigation and plan- ning of a hydropower project in a foreign country. The Icelandic firm is working on the appraisal of a 10—20 MW power plant for Jakobshavn in Greenland jointly with a Danish engi- neering firm. The Icelandic firm was engaged with particular reference to their experience in the design and con- struction of small scale power stations in northern countries. Geoscientific work for hydropower projects has primarily been in the hands of Icelandic geologists through the decades, but until 1974 foreign con- sultants supervised some parts of the research work for the large power pro- jects. GEOTHERMAL DEVELOPMENT Unlike the hydropower development the geothermal work has almost entirely been in the hands of Icelandic scientists and engineers. The main reason for this of course is that Iceland is one of the pioneer countries in the world in harn- essing geothermal energy and there ex- isted no foreign experts in this field in the early days of the development. Geothermal energy is very important for the national economy of Iceland as over one third of the net energy consumption of the country is from geothermal resources. Most of the geothermal energy is used for space heating. The total installed capacity of geothermal power in Iceland in 1982 is shown in Table 2. The installed thermal capacity Table 2. Installed capacity of geothermal power in Iceland in May 1982 Capacity Type of utilization MWt MWe Space heating 836 Greenhouses 51 Swimming pools 21 Industrial 50 Fish culture 2 Electricity 41 960 41 Note: The installed thermal capacity for space heating is calculated with a disposal temperature of 35°C, which is common in the space heating systems in Iceland. (total 960 MWt) is calculated with a disposal temperature of 35°C which is common in the space heating systems in Iceland. Using the average air temperature in Iceland 5°C as the reference temperature the total would be approximately 1480 MWt (3). In 1982 about 75% of the population lived in houses heated by geothermal water. The district heating systems are general- ly owned and operated by the municipalities. The Municipal Heating Service of Reykjavik serves about 114,400 people and is the largest geothermal heating service in the world with an installed capacity of about 520 MWt (assuming 35°C as the disposal temperature). Its operation started in

x

Tímarit Verkfræðingafélags Íslands

Beinir tenglar

Ef þú vilt tengja á þennan titil, vinsamlegast notaðu þessa tengla:

Tengja á þennan titil: Tímarit Verkfræðingafélags Íslands
https://timarit.is/publication/860

Tengja á þetta tölublað:

Tengja á þessa síðu:

Tengja á þessa grein:

Vinsamlegast ekki tengja beint á myndir eða PDF skjöl á Tímarit.is þar sem slíkar slóðir geta breyst án fyrirvara. Notið slóðirnar hér fyrir ofan til að tengja á vefinn.